Building Update 10-17-2010

The stone is going up on the columns that support the canopy of the new west entrance.

The face brick is almost finished on the elementary section.

New brick and facade are going up quickly on the 13th Street section.

The concrete floor has been poured in the lower part of the elementary section.  Electricians are currently working on running conduit  through the elementary auditorium before they pour that floor.

This is the new Bookstore.  Windows will be installed between the steel on the right (west) side.

Lines for the walls have been marked in the preschool section, and the studs should be going up soon.

Posted in Building Updates | Comments Off

Building Update 10-5-2010

This is the new cross on the outside of the chapel area facing 13th street.

More steel has gone up on the new addition.  Today they are working on the steel in the cafe and bookstore sections.

The new decorative block has started going up on the youth section.

This is the new elementary auditorium.

The outside walls are almost complete on the elementary section.  The decorative block is being put on and steel will lifted into place within the next few weeks.

This is one of the two sets of stairs that goes to the second level of the elementary section.

This is looking down the grand hallway that connects everything together in the new addition.

Posted in Building Updates | Comments Off

Video Update

Video Update from Sunday, 9-19-2010

Posted in Building Updates, Video Updates | Comments Off

Building Update 9-11-2010

The west parking lot was finished on Thursday and painted on Friday morning.

Spancrete was installed this last week for the 2nd floor of the elementary section.

This is the roof decking being placed on the preschool section.

Plumbing is also being installed in the preschool area.

More of the face brick arrived this week.


This is the framing for a new cross on the 13th Street side of the chapel.

Posted in Building Updates | Comments Off

Building Update 9-7-2010

Last week we saw more steel lifted into the preschool area and they have also started building the steel structure to support the second floor of the elementary section.

These are the foundations for the sidewalk overhang on the west side of the building.

This is a view of the classrooms in the elementary section.

Medians and sidewalks were poured last week in preparation for asphalt this week.