Monthly Archives: August 2010

Building Update 8-28-2010

Steel for the preschool area arrived this last week and workers have begun lifting it into place and welding it together. Work continues on the parking lot.  This last week they finished digging out parts of the old lot to … Continue reading

Posted in Building Updates | Comments Off

Building Update 8-19-2010

This has been a busy week on the building site.  They started working on another big portion of the parking lot as walls for the new section continue to rise.  Steel work is scheduled to start next week. More foundations … Continue reading

Posted in Building Updates | Comments Off

Video Update

Video update from Sunday 8-15-2010

Posted in Building Updates, Video Updates | Comments Off

Building Update 8-11-2010

More parking is complete!  There are a total of 325 new parking spaces to the west by I94 and to the south by the water retention pond.  Crews finished paving these sections yesterday, and painted the stripes earlier this afternoon.

Posted in Building Updates | Comments Off

Building Update 8-10-2010

Asphalt is being laid today on the expanded parking lot to the west by I94. This should be striped and ready to use by Sunday! Walls for the elementary section are going up fast. These are the foundations for the … Continue reading

Posted in Building Updates | Comments Off