Monthly Archives: September 2010

Video Update

Video Update from Sunday, 9-19-2010

Posted in Building Updates, Video Updates | Comments Off

Building Update 9-11-2010

The west parking lot was finished on Thursday and painted on Friday morning. Spancrete was installed this last week for the 2nd floor of the elementary section. This is the roof decking being placed on the preschool section. Plumbing is … Continue reading

Posted in Building Updates | Comments Off

Building Update 9-7-2010

Last week we saw more steel lifted into the preschool area and they have also started building the steel structure to support the second floor of the elementary section. These are the foundations for the sidewalk overhang on the west … Continue reading

Posted in Building Updates | Comments Off