The stone is going up on the columns that support the canopy of the new west entrance.

The face brick is almost finished on the elementary section.

New brick and facade are going up quickly on the 13th Street section.

The concrete floor has been poured in the lower part of the elementary section.  Electricians are currently working on running conduit  through the elementary auditorium before they pour that floor.

This is the new Bookstore.  Windows will be installed between the steel on the right (west) side.

Lines for the walls have been marked in the preschool section, and the studs should be going up soon.