This will be the fireplace in the cafe. It sits on a small platform that will be used as nice seating area and can also be used as stage for special events.
-
Recent Posts
Archives
Categories
Oak Creek Assembly of God
Meta
This will be the fireplace in the cafe. It sits on a small platform that will be used as nice seating area and can also be used as stage for special events.
The new building is now fully enclosed. WE Energies connected the power last week so the building is now being heated and is drying out.
Part of enclosing the building was finishing the window install in the dining area on the west side of the building.
Much of the framing has gone up in the grand hallway that connects all the new sections.
The framing has also gone up the food service area and the coffee bar.
This is the entrance to the elementary chapel.
This is the entrance to the new building from the current building. Behind the yellow wall is the current nursery section.
Walls are going up in the preschool area. This is the main hallway that wraps around the preschool chapel.
The concrete floors have been poured in the food service and dining areas. Windows should be going in soon.
This is the elementary section. They are continuing work on sprinkler systems and heating ducts.
This is the mall – the main hallway that runs through the new building connecting the nurseries, elementary, preschool, bookstore and food service areas.
Roofs continue to be installed on the new building in preparation for winter.
The main electrical panels are being installed.
Walls, heating ducts and sprinklers are all being installed in the preschool section.
Windows have been put into place in most of the elementary and preschool sections.
Plumbing and electrical lines are being laid in the new food serving section. 