As you enter through the north driveway, you’ll notice the brick and metal facade is being removed from the older part of the building. This will make room for bigger windows and new brick to unify the look of the entire campus. When the project is completed, this will be the new youth center and include an auditorium, cafe, game room, and patio.
Concrete foundations are being poured for the new pre-school area on the south-west side of the campus.
This is where the new building will meet the current building. Foundations are almost ready to be poured.
New parking lot lights are almost ready to be installed. This will be the expanded parking lot to the south by the field.
After a night of storms and heavy rain, the new water retention pond is doing its job. 